The ₹1,86,000 crore Race to Unclog India's Renewable Grid

India has approved the ₹1,86,000 crore PM-DHARA initiative to build intra-state transmission corridors and deploy 50 gigawatt-hours of battery storage to connect 135 gigawatts of green power. The mandate addresses severe grid congestion that caused over two terawatt-hours of clean electricity to be curtailed in 2025 alone. However, severe shortages of specialized transformer steel and protracted construction timelines mean transmission bottlenecks will persist for years before relief arrives.

The ₹1,86,000 crore Race to Unclog India's Renewable Grid

Executive Synthesis

In late September 2026, the Union Cabinet of India authorized a seminal infrastructure initiative that fundamentally alters the trajectory of the nation’s power sector. The PM-DHARA (PM-Developing Harmonized and Accelerated Renewable-energy Access) scheme, officially promulgated as the Green Energy Corridor Phase-III (GEC-III), commands a staggering total project outlay of Rs. 1,86,405 crore (approximately $22.3 billion). Targeting full implementation by the fiscal year 2032-33, the initiative is meticulously engineered to rectify the widening spatial and temporal asymmetries between India’s hyper-accelerated renewable energy generation capacity and its lagging power evacuation infrastructure. The scheme serves as the critical enabler for India’s ambitious macroeconomic targets of achieving 500 GW of non-fossil fuel capacity by 2030 and an ultimate 900 GW by 2035.

The architecture of PM-DHARA is bifurcated into two foundational pillars. The first is a Rs. 1,36,378 crore capital injection designated for the development of Intra-State Transmission Systems (InSTS) capable of evacuating up to 135 GW of renewable energy across various states and union territories. The second pillar, representing a paradigm shift in domestic grid management, is a Rs. 50,000 crore allocation for the procurement and deployment of 50 GWh of Battery Energy Storage Systems (BESS). Recognizing the immense financial strain this infrastructure would typically impose on regional power distribution companies (DISCOMs), the central government has structured the scheme to include Rs. 54,082 crore in Central Financial Support (CFA). This structural subsidy is designed to absorb a significant proportion of the intra-state transmission charges, thereby preventing acute tariff shocks for end-consumers and preserving the commercial viability of the wider utility sector.

However, rigorous macroeconomic analysis, supported by credit rating assessments and supply chain diagnostics, indicates that while the policy framework and capital commitments are unprecedented, the physical execution of the scheme faces formidable structural headwinds. Global supply chain bottlenecks—most notably the acute deficit of Cold Rolled Grain Oriented (CRGO) electrical steel required for high-voltage power transformers—threaten to stretch lead times and inflate capital costs, potentially introducing a significant time lag before the benefits of PM-DHARA materialize.

This comprehensive report evaluates the PM-DHARA scheme across multiple dimensions. It analyzes the macroeconomic imperatives driving the investment, the historical context of the Green Energy Corridor program, the regulatory mechanics of the Tariff-Based Competitive Bidding (TBCB) framework, the transformative implications of the 50 GWh BESS mandate, the systemic vulnerabilities within the capital goods supply chain, and the resultant competitive landscape for principal corporate beneficiaries including Power Grid Corporation of India (PGCIL), Adani Energy Solutions, Transformers & Rectifiers India, and KEI Industries.

The Macroeconomic Imperative: The Grid Squeeze and India’s Energy Transition

The genesis of the PM-DHARA scheme lies in a growing crisis of grid latency. India has aggressively expanded its renewable energy portfolio, successfully crossing the 250 GW non-fossil installed capacity milestone in late 2025, which translates to over 50% of the country’s total electricity installed capacity. Yet, the rapid deployment of solar and wind generation assets, which can typically be constructed and commissioned within 18 to 24 months, is drastically outpacing the development of transmission corridors. High-voltage transmission lines require extended, multi-year timelines due to complex route planning, right-of-way (RoW) acquisition disputes, environmental clearances, and protracted equipment procurement cycles.

This chronic asymmetry has resulted in substantial power curtailment, a scenario wherein generated zero-carbon electricity cannot be injected into the grid due to localized congestion, voltage instability, or a lack of load-balancing capacity. Empirical data highlights the severity of this bottleneck. In the first quarter of 2026 alone, an estimated 300 GWh of renewable electricity was forcibly curtailed due to transmission constraints, accounting for nearly two-thirds of the country’s total renewable energy curtailment during that period. Extrapolating to the broader timeline, India curtailed approximately 2.3 TWh of clean electricity in 2025, a volume sufficient to power 400,000 homes for an entire year. In highly concentrated renewable generation zones, such as Rajasthan, curtailment rates escalated dramatically, rising from 8.5% early in the year to over 51.5% during peak generation months. Across the industrialized states of Gujarat and Maharashtra, peak solar generation hours routinely witness 10% to 30% of potential output being rejected by the grid.

Credit rating agencies have identified this grid infrastructure deficit as the primary risk vector for India’s energy transition. S&P Global Ratings, in its October 2026 assessment titled "Indian Renewables: Dhara's Benefits Will Come With A Gap," noted that while the capital injection of the PM-DHARA scheme is precisely targeted at the weakest links of the renewables rollout, the benefits will manifest with a significant operational time lag. S&P analysts project that renewable generation capacity additions will continue to outpace grid connectivity through the end of the decade. Consequently, despite the ₹1,86,000 crore intervention, localized curtailment will remain a structural friction point until the newly mandated InSTS infrastructure reaches commercial operation.

The macroeconomic calculus underlying PM-DHARA is fundamentally an exercise in risk mitigation and capital preservation. By preemptively financing the evacuation infrastructure capable of handling 135 GW of variable renewable energy, the government aims to restore and sustain developer confidence. When independent power producers (IPPs) face persistent curtailment, the expected internal rate of return (IRR) on solar and wind assets deteriorates rapidly, which in turn threatens future foreign direct investment and domestic capital inflows into the sector. The state’s decision to assume a significant portion of the capital expenditure through the Rs. 54,082 crore CFA socializes the cost of grid expansion, preventing the financial burden from fracturing the already precarious balance sheets of state power distribution companies.

Historical Context: The Evolution of the Green Energy Corridors

To fully contextualize the scale and ambition of PM-DHARA, it is necessary to examine the preceding phases of the Green Energy Corridor (GEC) initiative. Stemming from a 2012 study by the Power Grid Corporation of India Limited (PGCIL), the GEC program was launched in 2015 by the Ministry of New and Renewable Energy (MNRE) to modernize a national grid that was historically designed for steady, dispatchable thermal baseload, rather than the erratic and geographically dispersed nature of large-scale renewable generation.

The first phase, GEC-I, was approved with a target of establishing 9,700 circuit kilometers (ckm) of intra-state transmission lines and 22,600 MVA of substation capacity to evacuate approximately 24 GW of renewable energy across eight resource-rich states: Andhra Pradesh, Gujarat, Himachal Pradesh, Karnataka, Madhya Pradesh, Maharashtra, Rajasthan, and Tamil Nadu. GEC-I was financed with a total project cost of Rs. 10,141.68 crore, supported by a 40% central grant, a 40% loan from the German development bank KfW, and 20% equity from the respective State Transmission Utilities (STUs). While highly successful in states like Rajasthan and Tamil Nadu, the execution of GEC-I faced persistent delays stemming from land acquisition and forest clearance hurdles, requiring extensions through 2024 and 2025 for several participating states.

The second iteration, GEC-II, was implemented to integrate an additional 20 GW of renewable energy capacity. It envisaged 10,750 ckm of transmission lines and 27,500 MVA of substation capacity across seven states, utilizing a similar central funding mechanism to offset transmission charges. Concurrently, a massive inter-state transmission system component was initiated under GEC-II to evacuate 13 GW of renewable energy from the Union Territory of Ladakh, incorporating 12,000 MWh of battery storage and high-voltage direct current (HVDC) terminals, carrying a project cost exceeding Rs. 20,773 crore.

PM-DHARA (GEC-III) dwarfs its predecessors in both scale and technological sophistication. While GEC-I and GEC-II focused primarily on lines and substations to manage a combined 44 GW of generation, GEC-III targets the evacuation of 135 GW of capacity. More critically, it embeds energy storage directly into the transmission architecture on a massive scale, moving beyond simple power evacuation toward active grid firming and load-shifting.

ParameterGEC Phase-IGEC Phase-IIPM-DHARA (GEC Phase-III)
Approval/Launch Year20152021-22September 2026
Target RE Evacuation~24 GW~20 GW (plus 13 GW Ladakh)Up to 135 GW
Total Financial OutlayRs. 10,141 Crore~Rs. 12,031 Crore (InSTS)Rs. 1,86,405 Crore
Central Financial Assistance40% of Project Cost33% of Project CostRs. 54,082 Crore (~29%)
Dedicated BESS IntegrationNone12 GWh (Ladakh Inter-state)50 GWh (Intra-state network)
Primary Focus AreasBasic grid integrationExpanding state capacityHarmonized access, Storage, Smart Grids

Source Data: Aggregated MNRE and PIB Official Disclosures.

PM-DHARA Architectural and Financial Modalities

The Rs. 1,86,405 crore capital outlay of the PM-DHARA scheme represents a highly structured financial intervention designed to catalyze both public and private capital formation within the power sector. The Ministry of New and Renewable Energy estimates that this core transmission investment will leverage additional investments associated with the 135 GW of renewable generation assets, estimated at an ancillary Rs. 4.6 lakh crore, alongside further downstream investments in pumped storage and advanced grid management systems.

Structural Relief for State Utilities: The Role of CFA

At the heart of the scheme's financial viability is the Rs. 54,082 crore Central Financial Support (CFA). To comprehend the significance of this subsidy, one must examine the precarious financial mechanics of India's state power distribution companies (DISCOMs). In standard regulatory frameworks, the capital costs incurred by transmission utilities for building new lines and substations are recovered through regulated transmission tariffs, which are subsequently billed to the DISCOMs. The DISCOMs, burdened by legacy debts and chronically high Aggregate Technical and Commercial (AT&C) losses, are often unable to fully pass these escalating network costs onto retail consumers due to political sensitivities and rigid state tariff orders.

If the entire ₹1,86,000 crore cost of PM-DHARA were injected directly into the transmission tariff pool without mitigation, it would precipitate a severe escalation in the Annual Revenue Requirement (ARR) of the DISCOMs, leading to acute tariff shocks for industrial and residential end-users. The CFA acts as a vital macroeconomic shock absorber. By financing approximately 29% of the total project outlay via central grants, the government permanently removes this quantum of capital from the tariff recovery base. This structural subsidy directly depresses the intra-state transmission charges, supporting the affordability of electricity and improving the financial liquidity of the DISCOMs, which in turn ensures timely payments to upstream generation and transmission companies. Furthermore, the modernization of aged substations and the introduction of advanced reactive power management funded by the scheme will physically reduce technical line losses, providing further relief to the AT&C loss metrics.

Execution Frameworks: TBCB versus Cost-Plus Basis

The execution of the PM-DHARA mandate relies on a bifurcated procurement strategy overseen primarily by the State Transmission Utilities (STUs).

For greenfield projects—which involve the surveying, land acquisition, and construction of entirely new transmission corridors and substations—development will proceed strictly under the Tariff-Based Competitive Bidding (TBCB) framework. The TBCB framework utilizes a Build-Own-Operate-Maintain (BOOM) model. Under this structure, Bid Process Coordinators (BPCs) such as REC Power Development and Consultancy Limited (RECPDCL) and PFC Consulting Limited (PFCCL) structure specific transmission routes into Special Purpose Vehicles (SPVs). Private transmission developers then submit bids based on the lowest annualized transmission charges they are willing to accept over a concession period, typically spanning 35 years. The BOOM model effectively transfers the risks of construction overruns, financing costs, and long-term operational maintenance away from the state utilities and onto specialized private entities, ensuring capital efficiency and accelerated project delivery.

Conversely, brownfield projects—which encompass the upgradation, capacity augmentation, and network strengthening of existing transmission towers, lines, and substations—will be executed on a Cost Plus Basis (CPB). Under the CPB mechanism, the incumbent state transmission utilities undertake the capital works directly. Because brownfield upgrades are deeply integrated into live, proprietary grid networks where the ownership of new assets cannot be easily delineated from existing legacy infrastructure, carving them out for private competitive bidding is technically complex and introduces severe operational and safety risks. Under CPB, the state utility is guaranteed a recovery of its actual, prudently incurred project costs alongside an assured, regulated return on equity, subject to the approval of the respective State Electricity Regulatory Commission (SERC).

State-Level Regulatory Mandates and Thresholds

The efficacy of the TBCB mechanism under PM-DHARA relies heavily on the regulatory compliance of the state commissions. The Ministry of Power has issued stringent guidelines mandating that all new intra-state transmission systems exceeding a specific financial threshold must be developed through the competitive bidding route, rather than being awarded on a nomination basis to the incumbent state utility.

State Electricity Regulatory Commissions (SERCs) have established these threshold limits to foster private participation. For instance, the Maharashtra Electricity Regulatory Commission (MERC) and the Tamil Nadu Electricity Regulatory Commission (TNERC) have specified a threshold limit of Rs. 200 crore (excluding land and reinstatement charges) for projects to be routed through TBCB. Similarly, the Gujarat Electricity Regulatory Commission (GERC) has instituted a tighter threshold limit of Rs. 100 crore, while states like Punjab have set limits as low as Rs. 50 crore. These regulatory guardrails ensure that the vast majority of the greenfield capital allocated under the ₹1,36,000 crore InSTS component of PM-DHARA will be subjected to the rigorous price discovery of the private market, maximizing the impact of the central financial subsidy.

State-level dynamics will dictate the pace of deployment. States with massive renewable resource potential, such as Rajasthan, Gujarat, Tamil Nadu, and Maharashtra, serve as the primary execution grounds. Other states are actively re-architecting their energy blueprints to capitalize on GEC-III funding. Telangana, for example, has formally sought GEC-III support to nearly triple its renewable energy capacity from 10,642 MW in 2025-26 to 29,645 MW by 2029-30, requesting central funds to integrate 3,000 MW of new solar generation alongside 4,000 MW of dedicated battery storage.

The 50 GWh BESS Revolution: Transforming Intermittent Energy into Dispatchable Baseload

The allocation of Rs. 50,000 crore exclusively for the procurement and integration of 50 GWh of Battery Energy Storage Systems (BESS) represents the most technologically transformative aspect of the PM-DHARA scheme. Historically, the Indian grid relied on thermal baseload generation and hydro pumped storage to balance demand. However, the sheer volume of solar and wind capacity coming online requires instantaneous frequency regulation and massive time-shifting capabilities that traditional mechanical systems cannot provide with sufficient agility.

Operational Imperatives and Deployment Architecture

The PM-DHARA policy deliberately avoids a rigid, monolithic deployment strategy for the 50 GWh of storage. Instead, it permits batteries to be sited heterogeneously across the grid infrastructure, either directly at the renewable energy generation nodes (co-located) or at strategically vital load centers, substations, and transmission bottlenecks. This architectural flexibility allows the STUs to address four distinct operational imperatives:

  • Mitigation of Peak-Hour Curtailment: BESS installations can absorb excess solar generation during midday periods when the total power output threatens to breach the thermal limits of the transmission lines or the stability limits of the grid, thereby saving terawatt-hours of clean energy that would otherwise be discarded.
  • Time-Shifting for Evening Peak Supply: By storing zero-carbon electricity during the day, BESS units can discharge power into the grid during the critical evening hours (post-sunset) when solar generation drops to zero but residential and commercial electricity demand spikes to its daily maximum.
  • Transmission Decongestion and Deferral: Placing high-capacity storage at known transmission bottlenecks allows electricity to be stored locally during periods of high generation and transmitted later when the line capacity frees up. This capability can defer or entirely eliminate the need for expensive, time-consuming physical upgrades to certain transmission corridors.
  • Grid Intermittency and Frequency Regulation: Advanced BESS systems provide sub-second response times, injecting or absorbing real and reactive power instantaneously to maintain grid stability and voltage frequency amidst the inherent fluctuations of wind speeds and transient cloud cover over solar parks.

Tariff Discovery, Viability Gap Funding, and Domestic Manufacturing

The execution of the BESS mandate capitalizes on the recent successes of Indian regulatory agencies in establishing competitive price discovery for grid-scale storage. Pilot tenders conducted by the Solar Energy Corporation of India (SECI) and NTPC have established highly encouraging benchmarks. For example, SECI's landmark 125 MW / 500 MWh standalone BESS auction in late 2025 yielded tariffs as low as Rs. 2.75 lakh per MW per month, driven by intense bidding from entities like Coal India and Onward Solar Power. To bridge the gap between the cost of nascent storage technologies and the commercial realities of the grid, mechanisms like Viability Gap Funding (VGF) provide capital grants that compress the discovered tariffs to levels acceptable to DISCOMs.

Crucially, the demand generated by the 50 GWh PM-DHARA mandate acts as a massive demand-side anchor for India’s domestic battery manufacturing ambitions. India’s total requirement for battery storage is projected to escalate rapidly to 236.22 GWh by FY 2032, requiring an estimated ₹3,49,000 crore in investment. The government’s Rs. 18,100 crore Advanced Chemistry Cell (ACC) Production Linked Incentive (PLI) scheme is specifically designed to domesticate the manufacturing of lithium-ion cells and other advanced chemistries, strategically migrating the industry away from its historical dependence on Chinese imports. Established domestic players like Exide Industries and Amara Raja Energy & Mobility are currently constructing gigafactories to service this impending demand. By synchronizing the PM-DHARA deployment targets with the ACC PLI capacity ramp-ups, the government ensures that a significant portion of the Rs. 50,000 crore BESS allocation circulates within the domestic industrial ecosystem, fostering technological self-reliance and mitigating geopolitical trade risks.

Supply Chain Chokepoints: The CRGO Steel Crisis and Transformer Bottleneck

While the financial commitments and policy frameworks of PM-DHARA are robust, the physical execution of the scheme is highly vulnerable to severe global and domestic supply chain constraints. The most critical bottleneck threatening the entire transmission build-out is the acute scarcity of Cold Rolled Grain Oriented (CRGO) electrical steel, which in turn is paralyzing the delivery timelines of large power transformers.

The Metallurgical Deficit

Transformers, which are essential for stepping voltages up for long-distance transmission and stepping them down for localized distribution, require high-grade CRGO steel for their internal magnetic cores. CRGO steel accounts for 30% to 40% of the total material cost of a transformer. It is exceptionally difficult to manufacture, requiring specialized metallurgical processes, strict silicon alloying (typically 3-3.2%), and high-temperature annealing to achieve the necessary magnetic permeability and ultra-low energy loss characteristics.

The supply-demand asymmetry in India is severe. As of the FY 2023-24 period, India’s annual demand for CRGO steel stood at approximately 400,000 metric tonnes. However, domestic production—primarily concentrated at a single operational facility (JSW JFE Electrical Steel in Nashik)—contributed a mere 50,000 metric tonnes, satisfying only 10% to 12.5% of national demand. To bridge this massive deficit, India relies on importing roughly 239,000 metric tonnes annually from major global producers in China, Japan, Russia, and South Korea. Even factoring in these extensive imports, the Indian market suffers from a chronic structural shortfall of nearly 30%, a deficit verified by the Global Trade Research Initiative (GTRI).

CRGO Steel Market Metric (FY 2023-24)Volume (Metric Tonnes)Percentage of Total Demand
Total Estimated Indian Demand~400,000 MT100%
Domestic Production (JSW JFE, etc.)~50,000 MT12.5%
Total Imports (China, Japan, Russia, SK)~239,000 MT59.7%
Structural Supply Shortfall~111,000 - 122,200 MT~27.8% - 30.6%

Source Data: Aggregated Industry Reports and GTRI Data.

This profound material deficit is severely compounding the lead times for power transformers. Prior to the post-pandemic surge in global renewable energy infrastructure, a standard high-voltage power transformer could be procured in 24 to 30 months. As of mid-2026, delivery timelines have stretched to an unprecedented 128 to 144 weeks, with highly specialized extra-high-voltage (EHV) units and generator step-up transformers seeing order backlogs of up to four years. Consequently, global and domestic power transformer prices have surged by 77% since 2019, inflating the capital costs of TBCB projects and eroding the profit margins of EPC contractors.

Regulatory Friction and Trade Remedies

The supply chain fragility is further exacerbated by the domestic regulatory and trade environment. The Bureau of Indian Standards (BIS) enforces a Quality Control Order (QCO) mandating that all imported CRGO steel carry BIS certification. While intended to ensure grid reliability and equipment efficiency, the limited approved grade list under the BIS catalogue restricts access to the advanced ultra-low-loss and domain-refined materials required for the highest-efficiency green energy transformers.

Furthermore, the Directorate General of Trade Remedies (DGTR) has initiated sweeping anti-dumping investigations into CRGO steel imports originating from primary Asian and Russian suppliers. The prospect of retrospective tariffs or newly imposed import duties between 2026 and 2030 threatens to introduce extreme cost volatility into the market. For engineering, procurement, and construction (EPC) contractors and private transmission developers bidding under the TBCB route, pricing fixed-tariff contracts for a 35-year operational horizon becomes highly precarious when the cost of the most critical raw material is subject to geopolitical shifts and sudden trade-remedy disruptions. While large-scale domestic production capacity expansions are underway, metallurgical complexity dictates that these new mills are unlikely to reach sufficient commercial scale until FY2028 at the earliest. Consequently, the initial, critical years of PM-DHARA execution will be forced to navigate a severely constrained and inflationary hardware market.

Corporate Beneficiaries and Competitive Landscape

The ₹1,86,000 crore capital injection authorized under PM-DHARA will cascade aggressively through the Indian utility and capital goods sectors, providing unprecedented, decade-long order book visibility for ecosystem players. The financial impact spans primary transmission asset developers, specialized heavy electrical equipment manufacturers, advanced cabling enterprises, and agile EPC contractors.

Power Grid Corporation of India Limited (PGCIL)

As the central transmission utility, PGCIL operates as the primary anchor and ultimate beneficiary of India’s grid infrastructure expansion. PGCIL holds a dominant position, commanding roughly 84% of the inter-state transmission system (ISTS) and holding approximately 44% of the tariff value of all competitively bid projects since the inception of the TBCB mechanism. The launch of PM-DHARA provides PGCIL with a vastly expanded theater of operations within the Intra-State (InSTS) domain, where it can leverage its unparalleled scale and balance sheet.

Financially, PGCIL is uniquely positioned to absorb massive capital outlays. The company has sustained its aggressive FY27 capex guidance at Rs. 37,000 crore, while pushing near-term capitalization targets (assets turned commercially operational) to Rs. 30,000 crore. Demonstrating its unmatched execution capabilities, PGCIL deployed a record capital expenditure of Rs. 39,967 crore in FY26, far exceeding its initial guidance. Looking ahead, management has outlined a monumental seven-year capital expenditure pipeline extending to ₹3,00,000 crore, directly aligning with the macroeconomic grid targets of 2032-2035. With the lowest cost of capital among domestic developers and a vast existing network offering significant brownfield synergies, PGCIL is fundamentally equipped to secure and execute the largest and most complex greenfield corridors proposed under GEC-III.

Adani Energy Solutions Limited (AESL)

In the private sector, Adani Energy Solutions operates as the most aggressive challenger to PGCIL’s dominance. AESL has rapidly expanded its portfolio of high-value transmission assets, most recently securing the critical 7 GW Khavda renewable transmission corridor in Gujarat via an electronic reverse auction, winning with the lowest quoted transmission charges of ₹2,391.77 crore.

AESL’s financial performance underscores its operational momentum and aggressive scale-up. In its Q2 FY27 results, the company reported a massive 53% year-over-year surge in consolidated revenue to ₹10,070 crore, driven by a 52% expansion in the core transmission segment and a 111% surge in revenues from its burgeoning smart metering platform. Operating EBITDA registered a 35.5% increase to ₹3,100 crore, maintaining a highly lucrative margin profile of 30.8%. Most critically, AESL’s aggregate order book stands at a formidable ₹87,220 crore across 15 major projects, providing years of revenue visibility.

Furthermore, AESL is strategically pivoting into the BESS sector, leveraging its broader group synergies (e.g., Adani Green Energy) to deploy massive storage facilities, highlighted by the ongoing deployment of a 1.37 GWh BESS installation at the Khavda renewable energy park. Under PM-DHARA’s TBCB route, AESL’s proven execution capabilities, vertically integrated project management, and aggressive bidding strategies position it to capture a significant proportion of both the ₹1,36,000 crore InSTS outlay and the Rs. 50,000 crore BESS mandate.

Transformers & Rectifiers (India) Limited (TARIL)

The critical bottleneck in transformers translates directly into extreme pricing power and margin expansion for established, technically capable domestic manufacturers. Transformers & Rectifiers India (TARIL) is uniquely positioned in this landscape, possessing the advanced engineering capability to manufacture extra-high-voltage (EHV) power transformers up to the ultra-high 1200 kV class, alongside highly specialized furnace and rectifier transformers.

TARIL is proactively navigating the CRGO crisis and global supply chain disruptions through aggressive backward integration. By internalizing key production processes—such as transformer tank fabrication, insulation manufacturing, and the production of specific sub-components—TARIL aims to shorten lead times, compress its working capital cycle, and defend its gross margins against volatile external raw material costs. This strategy is yielding exceptional financial results; the company has recorded a 106% CAGR in profit over the last five years and expanded its order book to a record ₹6,630 crore (as of late 2026), backed by a massive installed manufacturing capacity of over 75,000 MVA per annum. As STUs in key states like Rajasthan, Gujarat, and Maharashtra begin executing their PM-DHARA allocations, TARIL’s established relationships with these regional utilities provide a distinct competitive advantage over foreign OEMs and smaller domestic players.

KEI Industries and Polycab India: The EHV Cable Duopoly

The physical evacuation of 135 GW of renewable energy requires vast quantities of Extra-High Voltage (EHV) and High Voltage (HV) transmission cables. The capital intensity is severe; each new gigawatt of renewable power typically necessitates 50 to 80 kilometers of EHV cable, costing between Rs. 5 crore to Rs. 8 crore per kilometer.

KEI Industries and Polycab India operate as the primary domestic beneficiaries in this high-barrier-to-entry segment, which requires stringent technical pre-qualifications and decades of proven operational track records. KEI Industries relies on its EHV cable portfolio as its primary margin driver, as EHV products yield significantly higher EBITDA margins compared to standard retail housing wires. While the company’s Q1 and Q2 FY27 results demonstrated robust top-line growth (with Q2 net sales up 38.5% year-over-year to Rs. 3,776 crore), severe capacity constraints have capped near-term volume expansion. The highly anticipated Sanand Phase 2 greenfield expansion, specifically designed to add Rs. 1,500 to Rs. 1,700 crore in dedicated EHV capacity, has experienced execution delays and is now slated to commence commercial production by March 2027. Despite these delays, management has maintained firm guidance for operating margins to expand toward 11.5% to 12% across FY27 and FY28 as the high-margin EHV sales scale up and the new Salarpur facility comes online. KEI’s robust institutional order book, standing at nearly Rs. 4,927 crore, provides substantial revenue visibility as the grid build-out accelerates.

Polycab India, holding a dominant 25% to 30% market share in the broader wires and cables sector, presents a diversified, massive-scale alternative. 75,000 crore, Polycab captures value across both the utility-scale grid build-out and the consumer-facing Fast-Moving Electrical Goods (FMEG) markets, utilizing its vast retail distribution network to generate immense cash flows that fund its heavy industrial expansions.

Corporate BeneficiaryCore Domain under PM-DHARAStrategic Advantage / Key Financial Metric
Power Grid Corp. (PGCIL)Prime Grid Developer (TBCB)FY27 Capex guidance: Rs. 37,000 cr. Lowest cost of capital; dominant ISTS share (84%).
Adani Energy Solutions (AESL)Grid Developer (TBCB), BESSOrder book: ₹87,220 crore. Aggressive expansion in HVDC and large-scale Khavda BESS.
Transformers & Rectifiers (TARIL)Power Transformers (up to 1200 kV)Order book: ₹6,630 crore. Capacity: 75,000+ MVA. Margin expansion via backward integration.
KEI IndustriesEHV / HV Transmission CablesAdding Rs. 1,500+ cr EHV capacity by Mar 2027. High barrier to entry; strong institutional order book.
Polycab IndiaTransmission Cables / Wires25%-30% total market share; massive cash flows from retail FMEG segment cross-funding capex.

Source Data: Aggregated Corporate Earnings Disclosures and Market Analyst Reports.

EPC and Secondary TBCB Market Dynamics

Beyond the tier-one developers, the TBCB model fosters a thriving secondary market for mid-sized Engineering, Procurement, and Construction (EPC) firms and specialized developers. Entities such as Resonia Limited (formerly Sterlite Grid 32), Techno Electric, and Dilip Buildcon are actively acquiring Special Purpose Vehicles (SPVs) auctioned by Bid Process Coordinators like RECPDCL and PFCCL.

For instance, the recent transfer of the Hampapura Power Transmission and Mekhali Power Transmission SPVs in Karnataka to Resonia and Dilip Buildcon highlights the liquidity and depth of this secondary TBCB market. These specialized firms acquire build-own-operate contracts to secure long-term, annuity-like transmission revenues over the 35-year concession periods, executing complex 400 kV substations and associated lines with greater agility than larger, slower-moving conglomerates. This vibrant secondary market ensures competitive tension during the bidding process, ultimately driving down the levelized tariffs paid by the DISCOMs.

Systemic Risks: DISCOM Health and Tariff Revisions

The ultimate success of the PM-DHARA scheme is inextricably linked to the financial health of the state power distribution companies (DISCOMs). While the Rs. 54,082 crore CFA subsidizes a massive portion of the initial capital cost, the ongoing payment of the remaining transmission charges—which provide the revenue stream for PGCIL, AESL, and the secondary SPV holders—relies entirely on the revenue realization of the DISCOMs.

If DISCOMs fail to reduce their Aggregate Technical and Commercial (AT&C) losses, or if state governments artificially suppress retail electricity tariffs for political expediency, a liquidity crisis could easily cascade upstream. When DISCOMs delay payments for transmission services, the debt-servicing capabilities of the transmission developers are compromised, which in turn cools future private participation in TBCB auctions. The modernization of the InSTS network under PM-DHARA will inherently reduce technical losses by replacing outdated, inefficient substations and lines, but the commercial losses (theft, unmetered usage, poor collection efficiency) require stringent state-level administrative reforms. Thus, the PM-DHARA capital injection must be viewed not as a standalone panacea, but as a critical infrastructural enabler that requires parallel, rigorous regulatory reforms at the state level to ensure the long-term financial solvency of the entire power value chain.

Strategic Outlook and Conclusion

The PM-DHARA scheme constitutes a necessary and profoundly transformative intervention in India’s energy transition trajectory. By committing ₹1,86,000 crore to the modernization of intra-state grids and the deployment of massive battery storage, the government recognizes that the primary bottleneck to decarbonization is no longer the levelized cost of solar panels or wind turbines, but the physical capacity of the electrical grid to transport, firm, and time-shift variable energy.

The inclusion of the 50 GWh BESS mandate is arguably the policy’s most forward-looking component. By integrating storage directly into the transmission planning framework, India is deliberately moving away from the highly inefficient paradigm of curtailing excess renewable generation. This mandate, synchronized with the domestic Advanced Chemistry Cell PLI scheme, is poised to catalyze a robust domestic battery manufacturing ecosystem, transforming intermittent renewables into dispatchable, baseload-equivalent assets while fostering industrial self-reliance.

However, the execution of GEC-III faces severe metallurgical and supply-chain headwinds that cannot be ignored. The profound global and domestic shortage of CRGO electrical steel, compounded by anti-dumping investigations and stringent BIS certification requirements, threatens to elongate power transformer lead times well past 2028. For the scheme to succeed within its ambitious FY 2032-33 timeline, the government must carefully balance necessary trade protectionism with the urgent need for critical infrastructure inputs, potentially necessitating strategic exemptions or heavily expedited capacity building in domestic high-grade metallurgical manufacturing.

For corporate stakeholders, PM-DHARA officially initiates a decade-long supercycle in capital goods, extra-high-voltage cabling, and transmission EPC. Tier-one developers like Power Grid Corporation and Adani Energy Solutions are positioned to dominate the expansive TBCB landscape, while specialized, high-moat manufacturers like Transformers & Rectifiers India and KEI Industries stand to achieve unprecedented order book scale and sustained margin expansion.

Ultimately, the PM-DHARA paradigm shifts the narrative of India’s energy transition. Success will no longer be measured solely by gigawatts of generation capacity announced or installed, but by the circuit kilometers of transmission lines successfully strung, the megawatt-hours of batteries synchronized to the grid, and the systemic, permanent reduction in curtailed clean electricity.

Sources

  1. Cabinet Approves ₹1.86 Lakh Crore PM-DHARA Scheme - Exampur exampurstore.com
  2. PM-DHARA Scheme m.govtschemes.in
  3. Cabinet approves Green Energy Corridor Phase-III scheme for pib.gov.in
  4. Can Rs 1.86 lakh cr fix the grid? Infrastructure lag threatens India's financialexpress.com
  5. Cabinet clears ₹1.8 lakh-crore Green Energy Corridor-III | India News hindustantimes.com
  6. Cabinet clears ₹1.86 trn green energy corridor scheme with battery business-standard.com
  7. Why India needs a ₹1.86 lakh crore smart-grid push for renewables livemint.com
  8. PM DHARA Scheme: Benefits, Budget, Objectives & Details govtschemesindia.com
  9. Green Energy Corridor Phase-III - Drishti IAS drishtiias.com
  10. Indian Renewables: Dhara's Benefits Will Come With A Gap spglobal.com
  11. India's CRGO Steel Supply Crisis 2026: What Transformer smsteels.org
  12. The Bottleneck Nobody Talks About in the Energy Transition niveshaay.com
  13. MINISTRY OF NEW AND RENEWABLE ENERGY - S3waas cdnbbsr.s3waas.gov.in
  14. annual report 2025-26 - Ministry of New And Renewable Energy mnre.gov.in
  15. Transmission | Ministry Of Power powermin.gov.in
  16. Cabinet Approves ?1.86 Lakh Crore PM DHARA Scheme to sanskritiias.com
  17. India's Renewables Plan; The Engine of Decentralized Finance spglobal.com
  18. Green Energy Corridor Phase-III Approved: ₹1.86 Lakh Crore Plan currentaffairs.adda247.com
  19. Final-GERC MYT Regulations - Discussion Paper energy.prayaspune.org
  20. MSEDCL-MYT-Order_Case_no_217-of-2024.pdf mahadiscom.in
  21. Forum of Regulators (FOR) - FICCI ficci.in
  22. Cabinet Approves ₹1.86L crore Green Energy Corridor-III Scheme saurenergy.com
  23. Maharashtra TBCB Transmission Project Guidelines | PDF - Scribd scribd.com
  24. Green Energy Corridor Phase-III gets INR 1.86 lakh crore outlay for propnewstime.com
  25. REC arm transfers two SPVs to private entities 03 JUNE 2026 recindia.nic.in
  26. Power transmission and distribution, and smart metering adanienergysolutions.com
  27. annual report 2025-26 - Ministry Of Power powermin.gov.in
  28. Tariff based Competitive Bidding Guidelines for Intra-State tantransco.org
  29. government of india - Ministry Of Power powermin.gov.in
  30. Order in Suo Motu Petition No. 2171 of 2023 for TBCB dtd ... - GERC gercin.org
  31. Current Affairs | National | NDTL Accreditation categories.epratibha.net
  32. TGPSC Current Affairs October 5th 2026 | KPIAS Academy kpiasacademy.com
  33. India's Green Energy Corridor Phase-III: Explained - JAKSON Group jakson.com
  34. PM-DHARA Scheme – Green Energy Transmission | GS II shankariasparliament.com
  35. Green Energy Corridor Phase-III - P.L. Raj IAS & IPS Academy plrajiasacademy.com
  36. RE Monthly Update March 2026 JMResearch | PDF | Solar Energy scribd.com
  37. a deep dive into battery energy storage system massivefoundation.org
  38. India Battery Energy Storage Systems Market Outlook to 2030 aloraadvisory.com
  39. India's battery storage demand to hit 236.22 GWh by FY32, require aninews.in
  40. Best Lithium & Battery Stocks in India To Watch Now in 2026 jarvisinvest.com
  41. List of Best Battery Stocks in India in 2026 - smallcase smallcase.com
  42. The transformer bottleneck no one's talking about manufacturingtodayindia.com
  43. India's Transformer Moment: Capturing the Global Grid Equipment onemint.com
  44. India's Transformer Core Steel Gap - MOOPEC moopec.com
  45. India CRGO Anti-Dumping Probe 2026 dls-crgo.com
  46. Large Power Transformer Market Size, Share, Trends & Forecast 2033 skyquestt.com
  47. 5 Stocks to Watch as Cabinet Approves Rs 1.86 Trillion Green equitymaster.com
  48. Power Grid Corporation of India Ltd. share price target and research trendlyne.com
  49. Power Grid Corp stock rallies 5% on healthy outlook; higher capex business-standard.com
  50. PGCIL sets initial FY27 capex guidance at Rs.37,000 crore - T&D India tndindia.com
  51. Power Grid Corporation of India images.moneycontrol.com
  52. AESL Deepens Its Footprint in Khavda with the Award of 7GW adani.com
  53. Adani Wins Push for 2.5 GW HVDC Link in Khavda Renewable saurenergy.com
  54. Adani Energy Solutions img.etimg.com
  55. Adani Energy Solutions Ltd (BOM:539254) (Q2 2027) Earnings Call gurufocus.com
  56. Adani Green Energy commissions the world's largest single-location adani.com
  57. Adani Green Energy expands battery storage capacity to 6.63 GWh adani.com
  58. Adani Group stock headed for 41% upside after multiple businesstoday.in
  59. Transformers & Rectifiers (India) Ltd. share price target and research trendlyne.com
  60. Transformers and Rectifiers (India) Ltd - Wikipedia en.wikipedia.org
  61. Transformer Stock in Focus After Company Plans ₹1,250 Crore tradebrains.in
  62. Transformers & Rectifiers India Ltd Analysis | PDF - Scribd scribd.com
  63. Transformers & Rectifiers India Ltd share price | About T R I L screener.in
  64. Best Wire Stocks in India 2026 | Polycab Havells Finolex Cables KEI univest.in
  65. KEIIndustriesLimited - InvestorStack investorstack.in
  66. KEI Industries Ltd. Analysis - Go India Stocks goindiastocks.com
  67. KEI Industries Limited Price: Quote, Forecast, Charts & News (KEI.NS) perplexity.ai
  68. KEI Industries Ltd. Stock price: Live updates | Tijori Finance tijorifinance.com
  69. Alpha | KEI Industries Ltd. – Equity Research Desk - FundsIndia fundsindia.com
  70. POWERGRID, Resonia and Dilip Buildcon acquire four TBCB powerpeakdigest.com
  71. INVESTOR PRESENTATION EARNING UPDATES Q3 & 9M FY 26 techno.co.in
  72. TGERC Retail Supply Tariff Order: FY 2025-26 tgerc.telangana.gov.in
  73. final report on study on analysis of tariff orders & other orders of state forumofregulators.gov.in

Disclosure: Abajaba publishes financial market analysis and news. This article is provided for educational and informational purposes only. The author(s) are not SEBI-registered analysts, brokers, or investment advisors. This is not investment advice. Always consult a SEBI-registered financial advisor before making trading or investment decisions. Past performance is not indicative of future results.